Starah Central
Road Access Project

Supply and place access roads and supply and execute structure pad

Back to ongoing projects
In ProgressProject 01 · Access Roads & Pads

Starah Central Road Access Project

Customer
Civil & Electrical Projects Contracting Co.
Location
KSA

Overview

The project involves the construction and preparation of civil infrastructure works for the project site in full compliance with Saudi Electricity Company (SEC) standards. The scope includes the supply of all required materials, earthworks, backfilling, grading, and compaction to ensure a stable foundation for the project facilities.

Scope of work

  1. 01

    Construction of Access Roads in normal soil conditions, including excavation, grading, supply of approved fill material, placement, and compaction.

  2. 02

    Construction of Structural Pads (40 m × 40 m), including the supply and placement of approved backfill material with a total thickness of 300 mm, compacted in two layers of 150 mm each, in accordance with SEC specifications.

  3. 03

    Construction of Finger Roads, including supply, placement, grading, and 300 mm backfilling compacted in two layers of 150 mm each, meeting all SEC quality and compaction requirements.

  4. 04

    Execution of all earthworks, leveling, and compaction using approved equipment and testing procedures to achieve the required density and performance standards.

All works are executed in accordance with the latest Saudi Electricity Company (SEC) standards, ensuring quality, durability, safety, and timely project completion.

Site photos

Field works on site for this package.

3 images

Starah Central Road Access Project site photo 1
Starah Central Road Access Project site photo 2
Starah Central Road Access Project site photo 3

Partnership

Need support on a similar scope?